Reuse existing pavement materials.
Reuse at a minimum, a percentage of existing pavement material by estimated volume as shown in Table MR-2.1. The materials considered in volume calculations can include but are not limited to hot mix asphalt (HMA), portland cement concrete (PCC), unbound granular base material and stabilized base material.

A calculation that shows the computed percent of material reused including the following four items at minimum:
Greenroads
Apr 16th, 2011
We'll check it out, thanks!
HelderB
Mar 18th, 2011
On page 366: Please check the text "... IS THAT IT IS reused for a lesser purpose ... "
You must be logged in to the Greenroads website in order to post comments on the manual. If you already have an account, please log in using the green login box in the upper right portion of the screen. If you do not have an account but wish to comment, please sign up for one here.
Thanks,
The Greenroads Team
You may also want to Comment on the manual or Rate a project.