EW-6: Habitat Restoration

3 points

Goal

  • Offset the destruction and deterioration of natural habitat caused by road construction. Restore and protect natural habitat beyond regulatory requirements.

Requirements

EITHER requirement must be met for credit.

Requirement 1: For projects required to mitigate habitat impacts through restorative practices:

  • Implement a restoration/preservation plan that restores and/or preserves more area by 5% beyond what is required such that:
    • Total area of restored and/or preserved habitat = 105% of total required mitigation area

    OR

  • Total restoration and/or restoration cost = 105% of total cost required for restoration/preservation due to the roadway project

OR

Requirement 2: For projects not required to mitigate habitat impacts through restorative practices:

  • Conduct a biological assessment of the pre‐development condition of the project site and surrounding ecosystem or watershed

AND

  • Implement a restoration plan that:

    • Restores an area equal to the total disturbed surface area of the roadway project. 

    • States quantifiable goals regarding at least one of the performance metrics outlined below. 

    • Describes ecological design or engineering elements that are expected, with reasonable professional certainty, to meet the goals stated above. 

    • Lists responsible parties for restoration activities and subsequent monitoring efforts. 

    • Lists sources of funding for restoration activities and subsequent monitoring efforts. 

    • Completes restoration activities prior to the roadway facility opens to traffic, ideally during project planning. 

    • Is signed and approved by the responsible parties or the project ecologist.

Documentation

  • Copy of the executive summary from the biological assessment.
  • Copy of the restoration/preservation plan, highlighting the boundaries of the restored areas and the roadway project. If offsite, provide separate plans showing both areas.
  • Copy of the schedule of restoration activities or preservation efforts demonstrating that the completion of all restoration activities and preservation efforts coincides with or occurs prior to opening to traffic.

 