EITHER requirement must be met for credit.
Requirement 1: For projects required to mitigate habitat impacts through restorative practices:
OR
Total restoration and/or restoration cost = 105% of total cost required for restoration/preservation due to the roadway project
OR
Requirement 2: For projects not required to mitigate habitat impacts through restorative practices:
Conduct a biological assessment of the preādevelopment condition of the project site and surrounding ecosystem or watershed
AND
Implement a restoration plan that:
Restores an area equal to the total disturbed surface area of the roadway project.
States quantifiable goals regarding at least one of the performance metrics outlined below.
Describes ecological design or engineering elements that are expected, with reasonable professional certainty, to meet the goals stated above.
Lists responsible parties for restoration activities and subsequent monitoring efforts.
Lists sources of funding for restoration activities and subsequent monitoring efforts.
Completes restoration activities prior to the roadway facility opens to traffic, ideally during project planning.
Is signed and approved by the responsible parties or the project ecologist.