Greenroads Pilot Project

Upper Arlington, OH Projects

 

Summary

Owner: City of Upper Arlington, OH
Contract Price: $2.14 Million (two contracts)
Project Segments:

Edgevale Road - 0.78 miles
Glenmere Road - 0.27 miles
Sunset Drive - 0.57 miles
Inverness Way - 0.12 miles
Eastcleft Drive - 0.66 miles

Greenroads Score: 27 Points

 

Description

The projects rated for the City of Upper Arlington were part of their 2010 Street Reconstruction Program. The program was broken into two phases with five different streets being resurfaced.  Designs and construction was similar for all projects and all streets scored the same according to this assessment. The program seeked to improve mobility throughout the City including project activities such as pavement preservation and maintenance, utility upgrades and minor sidewalk improvements. The first phase included Edgevale Road and Glenmere Road and used an alternative method to traditional paving called Full Depth Reclaimation.  The second phase of the 2010 Street Reconstruction Program involved the paving of Sunset Drive, Inverness Way, and Eastcleft Drive and also used Full Depth Reclaimation.

Inverness Way Reconstruction

Sunset Drive Reconstruction